INTRODUCTION
Definition
Surveying is the process of determining the relative position of natural and manmade features on or under the earth’s surface, the presentation of this information either graphically in the form of plans or numerically in the form of tables, and the setting out of measurements on the earth’s surface. It usually involves measurement, calculations, the production of plans, and the determination of specific locations.
The surveyor may be called on to determine heights and distances; to set out buildings, bridges and roadways; to determine areas and volumes and to draw plans at a predetermined scale.
Types
There are two major categories of surveying:
1. Plane Surveying .
Plane surveying deals with areas of limited extent and it is assumed that the earth’s surface is a plane and therefore no corrections necessary for the earth’s curvature.2. Geodetic Surveying.
Geodetic surveying is concerned with determining the size and shape of the earth and it also provides a high-accuracy framework for the control of lower order surveys. The highest standards of accuracy are necessary. Geodetic surveys cover relatively large areas (eg a state or country) for which the effects of earth curvature must be considered.
Branches
1. Topographic Surveys are concerned with the measurement and mapping of the physical features of the earth. These features are all natural and manmade features.
2.Engineering Surveys cover surveys carried out as part of the preparation for, and carrying out of, engineering works, including roads, railways, pipelines, drainage etc.
3. Cadastral Surveys are concerned with the measurement, definition and mapping and recording of property boundaries.
4. Hydrographic Surveys are those made for determining the shape of the bottom of lakes, rivers, harbours and oceans. They also include the measurement of the flow of water in streams and the estimation of water resources.
5. Aerial Surveys are made from an aeroplane, and for the purpose of mapping the terrain. The control for such a map is obtained from ground surveys, but the details are obtained from aerial photographs. This includes making measurements and interpretations from aerial photographs.
6. Astronomic Surveys are surveys made to determine the latitude, longitude and azimuth from observations to the stars.
7. Mining Surveys are those made to determine survey control for the development of both surface and underground mines within the mining industry, and the determination of volumes in mine production.
8. Computing is a specialised area of surveying where complex computer programs are used to solve problems within the surveying industry.
9. Consulting is another specialised area of surveying where specialist surveyors are hired for a short period of time to advise on the requirements for a specific task or to perform the specific surveying
2.Engineering Surveys cover surveys carried out as part of the preparation for, and carrying out of, engineering works, including roads, railways, pipelines, drainage etc.
3. Cadastral Surveys are concerned with the measurement, definition and mapping and recording of property boundaries.
4. Hydrographic Surveys are those made for determining the shape of the bottom of lakes, rivers, harbours and oceans. They also include the measurement of the flow of water in streams and the estimation of water resources.
5. Aerial Surveys are made from an aeroplane, and for the purpose of mapping the terrain. The control for such a map is obtained from ground surveys, but the details are obtained from aerial photographs. This includes making measurements and interpretations from aerial photographs.
6. Astronomic Surveys are surveys made to determine the latitude, longitude and azimuth from observations to the stars.
7. Mining Surveys are those made to determine survey control for the development of both surface and underground mines within the mining industry, and the determination of volumes in mine production.
8. Computing is a specialised area of surveying where complex computer programs are used to solve problems within the surveying industry.
9. Consulting is another specialised area of surveying where specialist surveyors are hired for a short period of time to advise on the requirements for a specific task or to perform the specific surveying
History of surveying
- It is quite probable that surveying had its origins in ancient Egypt. The Great Pyramid of Khufu at Giza was built c. 2700 BC, 755 feet long and 480 feet high. Its nearly perfect squareness and north-south orientation affirm the ancient Egyptians' command of surveying.
- Evidence of some form of boundary surveying as early as 1400 BC has been found in the fertile valleys and plains of the
- The Egyptians had the groma, which was used to establish right angles. It was made of a horizontal wooden cross, pivoted at the middle and supported from above. From the end of each of the four arms hung a plumb bob. A plumb bob is a shaped weight that hangs from a string. Because of the weight, the string will always be vertical.
- The Greeks used a form of log line for recording the distances run from point to point along the coast while making their slow voyages from the Indus to the Persian Gulf about 325 BC.
- The Greeks introduced the astrolabe, which is an instrument to measure the altitude of stars above the horizon, in the 2nd century BC. It took the form of a graduated arc suspended from a hand-held cord. A pivoted pointer that moved over the graduations was pointed at the star. The instrument was not used for nautical surveying for several centuries, remaining a scientific aid only.
- During their occupation of Egypt, the Romans acquired Egyptian surveying instruments, which they improved slightly and to which they added the water level and the plane table.
- About 15 BC the Roman architect and engineer Vitruvius mounted a large wheel of known circumference in a small frame, in much the same fashion as the wheel is mounted on a wheelbarrow; when it was pushed along the ground by hand it automatically dropped a pebble into a container at each revolution, giving a measure of the distance travelled. It was, in effect, the first odometer.
- Arab traders brought the magnetic compass to the west in the 12th century AD.
- Plane tables were in use in Europe in the 16th century. Surveyors practised the principle of graphic triangulation and intersection. In 1615 Willebrord Snell, a Dutch mathematician, measured an arc of meridian by instrumental triangulation.
- In 1620 the English mathematician Edmund Gunter developed a surveying chain, which was superseded only by the steel tape in the beginning of the 20th century.
- By the late 18th century modern surveying can be said to have begun. One of the most notable early feats of surveyors was the measurement in the 1790s of the meridian from Barcelona, Spain, to Dunkirk, France, by two French engineers, Jean Delambre and Pierre Méchain. This was to establish the basic unit for the metric system of measurement.
- Many improvements and refinements have been incorporated in all the basic surveying instruments. These have resulted in increased accuracy and speed of operations and have opened up possibilities for improved methods in the field.
- During the nineteenth century, the combination of a hot air balloon and a camera were used to produce maps and plans. It was difficult to survey large areas because the balloons were slow moving and a new photographic negative had to be loaded into the camera after each photograph was taken. In 1862 union soldiers used cameras mounted in hot air balloons to map behind the confederate lines.
- It was not until the turn of the twentieth century, with the developments of the aircraft and invention of the roll of photographic film, that aerial photographs started to be used extensively within the survey industry.
- The first light wave Electronic Distance Measurement instrument was developed in 1943 to measure the velocity of light. Once the velocity of light was known, it was then possible to reverse the process so that a distance could be measured.
- In 1954, the light wave was replaced by a radio wave to increase the distance that could be measured. In the late 1960s, lasers were first used with EDMs.
- In the mid to late 1970s, the United States of America sent their first Global Positioning System satellites into space. The final development was the extensive use of computers to perform most common data processing and recording of survey data.
Procedure of surveying
The following sequence of steps is commonly followed when carrying out a survey:
(i) Reconnaissance.
During the reconnaissance phase, the surveyor will obtain an overall picture of the area that the project will be conducted in. They will select where the control points will be located, the accuracy required for the control, and which survey instruments will be required for the project.
(ii) Measurement and Marking .
During the measurement and marking phase, the surveyor will perform all the observations in the field required to accurately determine the control points, as well as placing and observing to any temporary points such as wooden pegs. They would also perform any calculations from the observations, such as angular and linear misclose and area and volume calculations.
(iii) Plan Preparation.
During the plan preparation phase, the calculations that were performed from the field observations would be further enhanced and used to produce the final plans for the project.
1. Responsibility to the Task.
The surveyor is responsible for completing the task required in the most efficient manner and in the time available. All effort must be made to ensure that the information supplied by the surveyor is as accurate as is possible to complete the task. Not all tasks require the same order of accuracy. By an understanding of the task the surveyor must decide on the accuracy to be achieved.
2. Responsibility to the Client or Employer
The surveyor has a responsibility to the client or employer to produce what the client requires, within the budget restraints. This may need patience and tact in explaining to the client the limitations to a task.
3. Responsibility to the Community.
The surveyor has a responsibility to the community in general, to ensure that work undertaken by his team does not damage property or interfere with members of the community. Permission must be sought before accessing private property or before removing trees or shrubbery to enable survey measurements.
4. Responsibility to the team .
The surveyor, as the leader of the survey team, has a responsibility to the members of that team and must ensure that their needs are met regarding their leave, pay, OH&S etc. The surveyor has a responsibility to ensure that all members of the team receive the training needed, not only to complete the task at hand, but also to enable them to advance within their chosen professions.
The role of the surveyor is to perform the measurements necessary to complete any task required.
1. For the Cadastral Surveyor, the main tasks involve the determination of property boundaries.
2. For the Topographical Surveyor, the main tasks involve the location of detail on the earth’s surface for the production of maps.
3. For the Engineer Surveyor, the main tasks include the setting out of buildings, sewers, drains, bridges and roadways; determining areas and volumes of regular and irregular figures; the preparation of detailed drawings and plans.
4. For the Mine Surveyor, the main tasks include the setting out of mine lease boundaries and the calculation of end-of-month volumes.
Responsibilities of a Surveyor.
The responsibilities of the surveyor are many and varied, but can generally be reduced to the following:1. Responsibility to the Task.
The surveyor is responsible for completing the task required in the most efficient manner and in the time available. All effort must be made to ensure that the information supplied by the surveyor is as accurate as is possible to complete the task. Not all tasks require the same order of accuracy. By an understanding of the task the surveyor must decide on the accuracy to be achieved.
2. Responsibility to the Client or Employer
The surveyor has a responsibility to the client or employer to produce what the client requires, within the budget restraints. This may need patience and tact in explaining to the client the limitations to a task.
3. Responsibility to the Community.
The surveyor has a responsibility to the community in general, to ensure that work undertaken by his team does not damage property or interfere with members of the community. Permission must be sought before accessing private property or before removing trees or shrubbery to enable survey measurements.
4. Responsibility to the team .
The surveyor, as the leader of the survey team, has a responsibility to the members of that team and must ensure that their needs are met regarding their leave, pay, OH&S etc. The surveyor has a responsibility to ensure that all members of the team receive the training needed, not only to complete the task at hand, but also to enable them to advance within their chosen professions.
Role of a Surveyor
The role of the surveyor is that of the leader of the team. With that role come the responsibilities outlined above.The role of the surveyor is to perform the measurements necessary to complete any task required.
Tasks of a Surveyor
The tasks performed by a surveyor will depend on which branch of surveying they practise in. The most common tasks involve the determination of height and distances.1. For the Cadastral Surveyor, the main tasks involve the determination of property boundaries.
2. For the Topographical Surveyor, the main tasks involve the location of detail on the earth’s surface for the production of maps.
3. For the Engineer Surveyor, the main tasks include the setting out of buildings, sewers, drains, bridges and roadways; determining areas and volumes of regular and irregular figures; the preparation of detailed drawings and plans.
4. For the Mine Surveyor, the main tasks include the setting out of mine lease boundaries and the calculation of end-of-month volumes.
0 comments:
Post a Comment